A pre-installation checklist for plant engineers — covering footprint, electrical, compressed air, the three LN2 supply modes, and ventilation, drawn from 19 on-site surveys across three continents.
TL;DR — What You Need to Know Before Installation Day
- Reserve roughly 1.0 m × 0.6 m for the dosing cabinet plus 0.8 m operator-side clearance and 0.4 m rear clearance, with a separate 1.5–3.0 m² pad for the LN2 supply vessel within 4 metres of the dosing head.
- Provide three-phase 380 V at 50 Hz with neutral and earth on a dedicated 10 A breaker — total cabinet draw is under 200 W for the Siemens PLC, HMI, and solenoid valves.
- Run a 1/2″ instrument-air line at 5–7 bar gauge through a filter-regulator-lubricator; consumption is under 5 L/min but pressure dips will cause solenoid misfires.
- Match LN2 supply mode to daily consumption: liquid dewar under 100 L/day, microbulk 100–1,500 L/day, on-site generator above 1,500 L/day or for 24/7 plants.
- Provide at least 6 air changes per hour of ventilation in the dosing area, plus an oxygen sensor that alarms at 19.5% O₂ at worker height — because LN2 boil-off displaces oxygen.
I have lost count of the times a customer has called me two weeks before installation day to ask "how much floor space does it need?" and "can you run on 220 V?" The answers are in this article, and the answer to the second question is no — not reliably. Because the dosing cabinet's PLC, HMI, and cryogenic solenoid all share the same power bus, a voltage drop on start-up starves the solenoid of holding current and the injection time stretches.
This guide is the survey I send to every customer before I board a plane. If you are a plant engineer, a project manager, or a facility designer specifying an LN2 dosing system, the eight sections below will let you walk the floor with a tape measure and leave with a confirmed site readiness.
Footprint, Weight and Operator Clearance
The first thing I check on every pre-installation survey is whether the customer has actually cleared the floor space. Not the cabinet footprint on its own — the cabinet footprint plus the operator access, the cryogenic transfer hose radius, and the dewar pad.
What the Datasheet Does Not Tell You
A WYD-series ultra-high-speed LN2 dosing cabinet measures 1000 mm × 600 mm × 2000 mm and weighs 32 kg empty. Those numbers fit on a single A4 page and look tidy in a layout drawing. What the datasheet does not show is the working envelope around it:
I require 0.8 m of clearance on the HMI side because the operator needs to stand in front of the touch screen to read recipes, acknowledge alarms, and change the dose volume. I require 0.4 m on the back side because the vacuum-insulated transfer hose needs a gentle sweep radius — sharp bends at the back of the cabinet stress the bayonet fittings and cause leaks within 12 months.
Field note from a 2023 Indonesian water plant: The customer's engineer had reserved exactly the cabinet footprint — 1.0 m × 0.6 m — against a wall. When we arrived, there was no room to open the rear panel, no room for the dewar pad, and no room to route the compressed-air line without crossing the conveyor. We spent half a day reorganising the floor plan and another half day patching the wall anchor points. Since then I insist on a full working-envelope drawing signed by the customer's facility engineer before we ship.
Electrical Supply — Why 380 V Three-Phase Matters
The dosing cabinet runs on three-phase 380 V at 50 Hz with neutral and protective earth — that is 3 phase + N + G, the same supply that powers the filler itself. The cabinet draw is modest: under 200 W for the Siemens PLC, the HMI touch screen, the cryogenic solenoid coil, and the optional vacuum pump on the insulated line.
A dedicated 10 A breaker is enough. Two details that matter more than the amperage rating:
- Voltage tolerance must stay within ±10%. Anything below 360 V on start-up will cause the solenoid to chatter or hold open for one extra cycle, which doubles the dose on every container. I measure the supply at the cabinet terminals with a true-RMS meter before I energise.
- Do not share the breaker with VFD-driven equipment (conveyor motors, capper spindles, rinser pumps). The VFD switching transients couple back into the bus and corrupt the analog level signal from the dewar.
| Utility | Specification | Notes |
|---|---|---|
| Electrical supply | 380 V, 50 Hz, 3 phase + N + G | 10 A dedicated breaker; ±10% voltage tolerance |
| Power consumption | ≤ 200 W | PLC, HMI, solenoid, optional vacuum pump |
| Compressed air | 5–7 bar gauge, clean & oil-free | 1/2″ NPT supply, FRL required |
| Air consumption | ≤ 5 L/min | Pressure stability more critical than flow |
| Cryogenic supply pressure | 1.0–1.4 bar gauge | Lower than typical cylinder regs to reduce waste |
| Ambient temperature | 0–40 °C | Cold-room operation needs low-temp HMI |
| Ambient humidity | ≤ 90% RH non-condensing | Cabinet IP54 standard; IP65 optional |
| Ventilation rate | ≥ 6 air changes / hour | O₂ alarm at 19.5% at 1.5 m height |
Do not run a WYD-series dosing cabinet on single-phase 220 V. I have had three customers try to substitute a step-down transformer, and all three saw solenoid misfires at line speeds above 400 CPM. The cryogenic solenoid needs a true three-phase supply to hold its coil at rated current without thermal cut-out.
Compressed Air — Small Flow, Big Consequences
The cryogenic dosing solenoid and the pneumatic isolation valves on the LN2 supply line operate on instrument air at 5–7 bar gauge. The cabinet itself consumes under 5 L/min — a trivial flow by pneumatic standards. Because the solenoid opens for 8–35 ms per container, even a brief pressure dip causes a partial dose. A 200-millisecond pressure dip on a 600 CPM line means 2 containers are under-dosed before the regulator recovers.
Three rules I enforce on every install:
- Use a dedicated 1/2″ NPT instrument-air line. Do not tee off the capper's 3/4″ supply. The capper draws in pulses when spindles engage, and those pulses will starve the dosing solenoid at exactly the wrong moment.
- Install a filter-regulator-lubricator (FRL) within 1 m of the cabinet. The FRL protects the solenoid from moisture and oil carryover from the compressor, which would otherwise freeze inside the cryogenic solenoid and lock it partially open.
- Verify pressure under load, not at rest. Open the capper's air consumption while measuring pressure at the dosing cabinet FRL. If pressure drops below 5.0 bar, you need a separate receiver tank or a larger supply line.
The Three LN2 Supply Modes — and How to Choose
Choosing the wrong LN2 supply mode is the most expensive installation mistake I see — not because the equipment costs more, but because the wrong choice forces the customer to live with it for 5–10 years. The decision is driven by daily LN2 consumption and plant operating pattern:
Mode 1: Liquid Dewar (Under 100 L/day)
For small lines, pilot plants, or seasonal operations, a 180–240 L portable liquid dewar on a wheeled frame is the right answer. Footprint is about 0.7 m², no electrical connection, no compressed-air requirement. The downside is refill logistics: a 200 L dewar at full dose typically needs a refill every 3–5 days.
Best fit: Craft beverage lines, R&D facilities, contract packers running under 8 hours/day. Truck delivery access is required because the empty dewar is swapped for a full one by the gas supplier.
Mode 2: Microbulk Tank (100–1,500 L/day)
A microbulk tank is a stationary 1,000–3,000 L vessel installed on a concrete pad outside the building, with a vacuum-insulated transfer line running through the wall to the dosing station. The gas supplier refills on a scheduled route and the customer never handles a cylinder.
Best fit: Mid-size beverage plants, dairy and juice lines, water bottling facilities. The tank pad adds 2–3 m² outside the building, plus a wall penetration for the transfer line. Inside, only the dosing cabinet is visible — the bulk tank is out of the way.
Mode 3: On-Site Nitrogen Generator (1,500 L/day and above, or 24/7 plants)
For high-volume plants and continuous operations, an on-site pressure-swing-adsorption (PSA) or membrane nitrogen generator produces gaseous nitrogen on demand, with an integrated LN2 buffer for the cryogenic dosing. The generator itself runs on compressed air and three-phase power — no truck deliveries, no cylinder logistics, no boil-off losses from a bulk tank.
Best fit: Plants above 1,500 L/day, plants with 24/7 schedules, plants in regions where truck delivery is unreliable or expensive, and plants where continuous supply is critical. The trade-off is a higher capital cost and the need for a dedicated compressed-air supply (typically 7–10 bar at 200–400 L/min).
| Mode | Daily Consumption | Footprint | External Dependencies | Typical Use |
|---|---|---|---|---|
| Liquid dewar | Under 100 L/day | ~0.7 m² (inside) | Truck delivery every 3–5 days | Craft lines, pilot plants |
| Microbulk tank | 100–1,500 L/day | 2–3 m² (outside pad) + wall penetration | Truck delivery on scheduled route | Mid-size beverage / dairy lines |
| On-site generator | 1,500 L/day and above | 4–8 m² (mechanical room) | Compressed air + 3-phase power only | 24/7 plants, high-volume facilities |
Ventilation and Oxygen Monitoring — The Safety Layer You Cannot Skip
Liquid nitrogen boils off continuously, even from a well-insulated vessel. One litre of LN2 produces roughly 700 litres of gaseous nitrogen at room temperature. Because gaseous nitrogen is colourless and odourless, an oxygen-deficient atmosphere can build up around the dewar or dosing station before anyone notices the symptoms — dizziness, ringing in the ears, loss of coordination.
I have walked into two plants where the dosing station sat in a poorly ventilated corner and the operator complained of morning headaches. Both plants had oxygen levels below 19% at worker height within an hour of dosing startup. Both plants installed mechanical extraction within a week of our visit.
Three controls are mandatory on every install:
- At least 6 air changes per hour of ventilation. For a 100 m² dosing room with a 4 m ceiling, that is roughly 2,400 m³/hour of supply air. In a cold room or sealed packaging hall, you will need mechanical extraction — passive ceiling vents will not clear boil-off gas fast enough.
- An oxygen sensor at worker height (1.5 m above floor). The sensor should alarm at 19.5% O₂ and trip the dosing solenoid at 18.5% O₂. I always specify a sensor with a 5-year calibration interval, not the cheaper 1-year models — operators forget to recalibrate.
- An audible and visual alarm at the operator station. The alarm must be distinct from the line-running alarm so the operator can tell "low oxygen" from "capper jam" by sound alone.
Never install a dewar inside a sealed cold room. LN2 boil-off in a refrigerated space below 5 °C accumulates faster than it can be cleared by the cold room's own air circulation. We mandate an external dewar pad with a vacuum-insulated transfer line through the wall — even if the dosing station itself is inside the cold room.
Foundation, Levelling and the Floor Under the Dewar
The dosing cabinet itself is floor-standing and weighs only 32 kg empty — it does not require a poured foundation or anchor bolts. A level, clean concrete floor is enough, with the cabinet bolted down through rubber anti-vibration feet to prevent drift during conveyor operation.
The dewar pad is a different matter. A 1,000 L microbulk tank weighs about 1,500 kg empty and 2,400 kg full; a 3,000 L tank weighs 4,000 kg full. The pad must be:
- Level to within 2 mm/m in both directions. An unlevel dewar causes the internal pressure-build regulator to drift, which causes the dosing pressure to swing and the dose weight to vary.
- Raised 100 mm above the surrounding floor so any condensate or spill drains away from the tank rather than pooling at the base.
- Sloped 1–2% toward a drainage point if the floor is otherwise flat. LN2 spills form ice on contact with warm concrete, and that ice becomes a slip hazard within an hour.
Installation Schedule — What Fits in a Day
I plan every installation as a single 8–10 hour shift, with a half-day buffer for the unexpected. Here is how I break down the day:
| Activity | Duration | What Happens |
|---|---|---|
| Mechanical mounting | 1.5–2 hours | Position cabinet, anchor, level, align dosing head with conveyor |
| Utility hookup | 2–3 hours | Electrical, compressed air, LN2 transfer line, signal cables |
| PLC integration | 1.5–2 hours | Connect three signals from filler PLC, handshake test |
| Dose calibration | 1.5–2 hours | Three-speed test, weigh containers, trim injection time |
| Operator training | 1 hour | HMI walkthrough, alarm acknowledgement, refill procedure |
| Documentation handover | 0.5 hour | Sign commissioning report, file as-built drawings |
If you have not done the utility prep work before installation day — i.e. the electrical panel is not yet run, the compressed-air line is not yet tapped, the dewar pad is not yet poured — add 2–3 days to the schedule. Because the dosing cabinet is the last piece of equipment on the line, the customer's general contractor often leaves it for the end and skips the prep. I now require a photo of the prepared site 48 hours before I fly.
Five Pre-Installation Mistakes That Cost a Week of Schedule
To close, here are the site-readiness failures I see most often. Every one of them is preventable with a half-day walk-through two weeks before the install date.
- Floor space reserved for the cabinet alone, not the working envelope. The 1.0 m × 0.6 m cabinet footprint looks tidy in a 2D layout, but the operator needs 0.8 m of clearance and the dewar needs a separate pad. I have walked into plants where the dewar ended up in the loading dock.
- Single-phase 220 V supplied instead of three-phase 380 V. Sometimes the customer's electrician assumes "European machine, single phase" without reading the datasheet. Verify the supply at the panel before the install date.
- Compressed-air tapped off the capper supply. The capper pulses draw pressure down at the wrong moment. Run a dedicated 1/2″ line with its own FRL.
- Dewar pad poured 6 inches below floor level. The customer's mason poured the pad to match the floor rather than raised it 100 mm above. Condensate pooled and froze around the tank base. We had to chip out the concrete and re-pour.
- No oxygen sensor ordered with the ventilation upgrade. Mechanical extraction fans were specified but no monitoring. I now refuse to commission without an O₂ sensor on the wall, even if the customer pushes back on cost.
Avoid those five, do the utility prep two weeks ahead, and a single 8–10 hour shift is enough to bring the line into production. For a closer look at the cabinet itself and what arrives in the crate, watch the installation footage below or jump to the product page.
See It Installed on a Real Line
Installation is easier to plan when you can see it. We maintain a field video library of WYD-series dosing systems being mounted, hooked up, and commissioned across the plants we have worked with — beverage, dairy, water, juice, and PET carbonated soft drink.
Frequently Asked Questions
How much floor space does a liquid nitrogen dosing machine need?
A typical WYD-series dosing cabinet occupies roughly 1.0 m × 0.6 m of conveyor-side floor footprint, with a height of 2.0 m. Allow an additional 0.8 m of clearance on the operator side for the HMI access and an LN2 supply line, plus 0.4 m on the back side for the vacuum-insulated transfer hose. The bulk dewar or microbulk tank sits separately and adds another 1.5–3.0 m².
What electrical supply does an LN2 doser need?
Three-phase 380 V at 50 Hz with neutral and protective earth (3 phase + N + G). The cabinet draws under 200 W for the Siemens PLC, HMI, solenoid valves, and optional vacuum pump. A dedicated 10 A breaker is sufficient. Voltage tolerance should stay within ±10%; drops below 360 V cause solenoid misfire on high-speed dosing.
Does the dosing system need compressed air?
Yes. The cryogenic solenoid and the pneumatic isolation valves operate on clean, dry, oil-free instrument air at 5–7 bar gauge. A dedicated 1/2″ NPT supply line with a filter-regulator-lubricator (FRL) is standard. Typical consumption is under 5 L/min, so even a small reciprocating compressor can support a single dosing station.
Should I choose a liquid dewar, microbulk tank, or on-site nitrogen generator?
Choose liquid dewars for under 100 L/day consumption, microbulk tanks for 100–1,500 L/day, and on-site nitrogen generators for 1,500 L/day and above or for plants running 24/7. Each mode has different footprint, ventilation, and logistics requirements — dewars and microbulk need truck delivery access, while generators need compressed air and power but no truck access.
What ventilation does the dosing area require?
LN2 displaces oxygen as it vaporises, so the dosing and dewar area needs a ventilation rate of at least 6 air changes per hour. An oxygen sensor at worker height (1.5 m above floor) that alarms at 19.5% O₂ is recommended. In cold rooms or sealed packaging halls, plan for mechanical extraction near the dewar, not just passive ceiling vents.
Can the dosing machine be installed in a cold room or refrigerated warehouse?
Yes, with caveats. The cabinet itself handles 0–40 °C ambient without issue, but the cryogenic transfer line loses less heat in a cold room — which actually reduces boil-off. The operator HMI must be specified for low-temperature LCD operation (down to −10 °C). Avoid installing the dewar inside a sealed cold room because boil-off gas accumulates faster than passive ventilation can clear it.
How long does installation and commissioning take?
Mechanical mounting and utility hookup typically take 4–6 hours. PLC integration with the filler takes another 2–4 hours. The full commissioning — including three-speed validation, dose calibration, and operator training — is a single 8–10 hour shift. Plan for two days on site if you want a buffer for unexpected conveyor modifications.
What foundation work is needed before the dosing machine arrives?
The dosing cabinet is floor-standing and weighs about 32 kg empty — it does not require a poured foundation. However, the floor under the cabinet and around the dewar must be level to within 2 mm/m and able to support the loaded dewar weight (typically 1,500–4,000 kg). A 100 mm raised concrete pad is standard for the dewar stand.
Planning an LN2 Dosing Installation?
Send us your line layout and we will return a marked-up floor plan with cabinet position, dewar pad, utility connections, and ventilation requirements.